Rough Order-of-Magnitude (ROM)

A rough order of magnitude (ROM) estimate is an early cost range used to judge whether a project is worth pursuing before any meaningful design work begins.

At a glance
Also called
ROM, Class 5 estimate, concept screening
Used for
Screening a project in or out before design begins
Key fact
AACE: the final cost can land 50% below to 100% above a ROM
EXPECTED ACCURACY BY ESTIMATE CLASS (AACE)-50%-25%+25%+50%+75%+100%0Class 5ROM / concept screeningClass 4feasibilityClass 3budgetClass 2controlClass 1definitiveExample: a $16.7 million ROM for a 500-space garagecould land anywhere from about $8.3 million to $33.3 million.
Darker bars show the narrow end of each range, lighter bars the wide end. A ROM (Class 5) can miss by half on the low side or double on the high side; estimates tighten as design advances. Ranges per AACE International classification.

A ROM answers one question: is this project in the right financial neighborhood? It is built from historical costs, unit rates, and comparable projects rather than quantities taken from drawings, and it is only as good as the assumptions written next to it.

Try it
How wide is your number, really?

Set a ROM figure and watch the range around it. Each class below is a later, better-defined estimate of the same project.

Estimate classLow endHigh endProject defined
Class 5 (ROM)-20% to -50%+30% to +100%0 to 2%
Class 4-15% to -30%+20% to +50%1 to 15%
Class 3-10% to -20%+10% to +30%10 to 40%
Class 2-5% to -15%+5% to +20%30 to 75%
Class 1-3% to -10%+3% to +15%65 to 100%

Ranges from AACE International Recommended Practice 18R-97, estimate classes 5 to 1. Dollar figures are the slider value times those percentages.

Where ROM sits among estimates

Estimates tighten as design advances. AACE International’s estimate classification system places the ROM at Class 5, often called concept screening, prepared with roughly 0 to 2 percent of the project defined. AACE’s expected accuracy for a Class 5 estimate is wide: from 20 to 50 percent below the final cost to 30 to 100 percent above it. Budget estimates (Classes 4 and 3) narrow that range as programming and schematic design firm up, and definitive estimates (Classes 2 and 1) are built from detailed drawings and quantities.

A parking example

WGI’s 2026 Parking Structure Cost Outlook puts the national median construction cost of a parking structure at $33,300 per space, or $98.75 per square foot, up 6 percent from the prior year. A ROM for a 500-space above-grade garage starts near $16.7 million. Applying the full Class 5 range, the eventual cost could reasonably land anywhere from about $8.3 million to $33.3 million. That spread is the point: a ROM screens a project in or out, and it should never be dropped into a pro forma as if it were a bid.

The WGI figure is a national median for construction. Costs vary sharply by market (WGI’s range runs from Houston at the low end to San Francisco at the high end), below-grade parking costs considerably more, and land, design fees, financing, and equipment such as PARCS and EV charging sit on top.

Common ROM mistakes

  • Presenting a single number instead of a range.
  • Leaving out the exclusions, so readers assume land, soft costs, or technology are included.
  • Forgetting escalation. At 6 percent a year, a ROM prepared two years before construction is already stale.
  • Carrying the ROM forward unchanged after the program changes.