Best value procurement is a method of selecting a contractor or design-build team by weighing price together with non-price factors such as experience, technical approach, schedule and key personnel, using evaluation criteria and weights published in the solicitation, rather than awarding to the lowest bidder.
Low-bid procurement assumes that every responsive bidder will deliver the same thing, so price alone decides. Best value accepts that proposals differ in quality and lets the owner pay more for a better one, within the rules it publishes up front. It is common in design-build, where teams propose different designs, and in technology procurements where the solutions themselves differ.
Common approaches
- Weighted scoring. Technical and price scores are combined using published weights, for example 70 percent technical and 30 percent price.
- Adjusted price or value per point. Price is divided by the technical score, or adjusted by it, to find the most value per dollar.
- Tradeoff. Evaluators judge whether a higher-rated proposal is worth its higher price, as in the federal tradeoff process.
- Lowest price technically acceptable. Proposals must pass a technical threshold, then the lowest price wins. Often grouped with best value, though it behaves more like low bid.
What makes it work
- Criteria tied to what actually drives project success, not generic boilerplate.
- Trained evaluators and written scoring rationale, so awards hold up under protest.
- Price weights that reflect how much quality differences really matter for the project.
What to watch
- Protests. Subjective scoring invites challenges if the record is thin.
- Proposal cost. Teams spend heavily on proposals; stipends for unsuccessful shortlisted teams are common on large design-build work.
- Legal authority. Some public owners need statutory authority to award on anything but low bid.
The Parkonomics view
For parking technology, best value is often the difference between buying a system and buying a catalog. PARCS, guidance and enforcement platforms vary in integration, data access and upgrade path in ways a price sheet cannot show. A solicitation that scores those things, and says so up front, gets better proposals and a defensible award.