MacLeamy Curve

The MacLeamy curve is a diagram showing that a project team’s ability to influence cost and performance is highest at the start of design and falls toward construction, while the cost of making a design change rises over the same period.

At a glance
Named for
Patrick MacLeamy, who introduced it at the Construction Users Roundtable in 2004
Used to argue for
Front-loading design effort and integrated project delivery
Key fact
The same change costs a few lines on paper early and demolition after construction
THE MACLEAMY CURVECHEAP TO CHANGEAbility to influence cost and functionCost of a design changeFeasibilityConceptSchematicDesign dev.Constr. docsBuildOperate
Conceptual. Influence is highest at the start of design and the cost of change is highest after construction, so effort spent early buys the most. Adapted from the curve introduced by Patrick MacLeamy in 2004.

The curve is a conceptual picture, not a cost formula. Its point is timing: decisions that shape how a building works are cheapest while it is still a concept, and expensive once they are drawn into construction documents, bid, built and occupied. Architects and builders use it to justify moving design effort, and the people with the most specialized knowledge, earlier in the process.

Try it
When does the operator join?

Slide the parking operator’s arrival across the project phases and see which garage decisions are still open.

If the operator joins at concept, nearly every decision is still open. At construction, only signs, staffing, procedures and pricing remain, and every other change is rework.

Phases at which each decision becomes fixed are typical, not universal.

In parking

Driveway locations, ramp layout, column grid, clear heights, island locations and conduit routes are all fixed early, and all of them decide how a garage operates for decades. Yet the operator is often invited in at the far right of the curve, after the building is finished, when the job is to make it work. Bringing an owner’s parking consultant in at feasibility moves that knowledge to the cheap end of the curve.

The Parkonomics view

Every operating problem a garage has was once a cheap decision on a drawing. The curve is the simplest argument for paying for operational review early, and for writing operating requirements into design contracts and design-build criteria before the design is locked.